Stargate Abilene

Abilene data center: what has been built, and what the companies claim

The Stargate flagship in Texas, quarter by quarter from orbit.

Crusoe began building on the Lancium Clean Campus outside Abilene in June 2024, for Oracle and OpenAI. This guide sets satellite pictures of every quarter since 2023 beside what the companies have said about buildings, power, water and jobs, with a source and a date on every figure.

Aureum reference guide · Latest pass 4 Nov 2026

Watch the Abilene data center go up

Fifteen clear Sentinel-2 passes over the same 4.4 by 3.4 km frame, one for each quarter from mid-2023 to November 2026. Press play, or drag the slider.

Sentinel-2 picture of the Stargate data center site outside Abilene, Texas, 4 NOV 20264 NOV 2026
Sentinel-2 true colour, the clearest pass in each quarter, all cropped to the same frame. Contains modified Copernicus Sentinel data 2023 to 2026.

What the passes show: untouched scrub until early 2024; the first cleared ground on 5 June 2024; a graded pad with the footprints of two buildings by 10 September; two roofed buildings by 29 December 2024; a large pad to the south from March 2025, with six more buildings framed by August and roofed by the end of the year; all eight halls roofed by 26 March 2026; and from spring 2026, new ground cleared and large buildings rising south of the halls.

Status checkChecked

Is the Abilene data center finished?

The eight halls of the Stargate campus are roofed, with equipment beside them, and building continues to the south. How many buildings are switched on is a question the companies answer differently, and one a satellite cannot settle.

Aureum satellite pass
Eight roofed halls, with equipment along them, 4 Nov 2026Sentinel-2B at 17:25 UTC. A second build area south of the halls has been under construction since spring 2026.
Crusoe
A six-building second phase to bring the campus to 1.2 GW by end-2026Release of 27 March 2026, which also announced a separate 900 MW, two-building campus for Microsoft.Crusoe, 27 Mar 2026
Oracle and OpenAI
Eight buildings on 1,100 acres: one running, seven due by mid-2026Fact sheet of 23 September 2025, which also said a further 600 MW might follow nearby.Fact sheet, 23 Sep 2025
Epoch AI
About 0.3 GW operating, four of eight buildings (estimate)Site note updated 23 April 2026, projecting 1.2 GW by the fourth quarter of 2026.Epoch AI, 23 Apr 2026
Oracle's site page
Eight buildings, 4 million sq ft; workloads running within a yearThe page says its information is current as of January 2026 and will not be updated.Oracle
The Microsoft campus
900 MW in two buildings, first due mid-2027Crusoe, 27 March 2026, with land clearing under way. It is not one of the eight Stargate buildings.

This panel is the only part of the page tied to a date. Everything below it is background, with the period stated on every figure.

Fact file

Stargate Abilene at a glance

The background figures, each with who stated it and when.

Where
Lancium Clean Campus, Texas
Outside Abilene, in Taylor County (Crusoe and Lancium, July 2024; fact sheet, September 2025).
Builder
Crusoe
Owns, develops and operates the data center (Lancium, July 2024).
Cloud and customer
Oracle, for OpenAI
Runs on Oracle Cloud Infrastructure; OpenAI calls it the Stargate flagship (September 2025).
Financing
$3.4 billion joint venture
Blue Owl and Primary Digital Infrastructure funded the first two buildings (October 2024).
Buildings
Eight
On 1,100 acres, up to about 4 million sq ft (Oracle and OpenAI, September 2025).
First project
206 MW, two buildings
998,000 sq ft, leased to an unnamed Fortune 100 tenant (October 2024).
Campus power
1.2 GW
Crusoe's figure, first stated in July 2024 and repeated in March 2026.
Construction began
June 2024
Crusoe, September 2025. The first cleared ground shows in the 5 June 2024 pass.
First chips
June 2025
Oracle began delivering NVIDIA GB200 racks (Crusoe; OpenAI).
Grid
ERCOT
With GE Vernova gas turbines for backup power (fact sheet, September 2025).
Cooling
Closed-loop liquid
Non-evaporative, according to the September 2025 fact sheet.
Water
12,625 to 50,000 gallons
Per building a year: the September 2025 fact sheet against Oracle's January 2026 page.

Sources: Lancium (18 July 2024), Crusoe financing release (15 October 2024), Oracle and OpenAI fact sheet (23 September 2025), Crusoe (30 September 2025 and 27 March 2026) and Oracle (as of January 2026).

Where is the Abilene data center?

The Stargate data center is on the Lancium Clean Campus outside Abilene, in Taylor County, Texas (Lancium, 18 July 2024). Lancium assembled the land and the power connection; Crusoe owns, develops and operates the data center, and began building it in June 2024.

Search for an Abilene data center and you will find three projects, often run together:

  • The Stargate flagship: eight buildings on 1,100 acres, built by Crusoe and run on Oracle Cloud Infrastructure for OpenAI. This guide is about this campus.
  • A Microsoft campus next door: 900 MW in two buildings, announced by Crusoe on 27 March 2026, with land clearing under way and the first building due in mid-2027. It is not one of the eight.
  • Vantage's Frontier campus: another Stargate site, in neighbouring Shackelford County: 10 buildings on 700 acres, with the first due in the second half of 2026, according to the Oracle and OpenAI fact sheet of September 2025.
USDA aerial photograph of the future Stargate site outside Abilene in July 2022: scrub pasture crossed by dirt roads.
The site on 26 July 2022, before construction: scrub pasture and ranch roads, in the same frame as the satellite sequence. USDA National Agriculture Imagery Program, 60 cm, public domain.

What is Stargate building in Abilene?

Eight data center buildings, in the companies' latest descriptions. The project has been described in several ways as it grew, and the statements do not always agree.

What was saidWho, when
First phase200 MW, expanding across 1.2 GWCrusoe and Lancium, 18 Jul 2024
First project206 MW, 998,000 sq ft, two buildingsCrusoe, Blue Owl and Primary Digital, 15 Oct 2024
CampusEight buildings, 1,100 acres, up to about 4m sq ftOracle and OpenAI, 23 Sep 2025
Buildings runningOne building up and runningOracle and OpenAI, 23 Sep 2025
Buildings energisedThe first twoCrusoe, 30 Sep 2025
Expansion nearbyA potential further 600 MWOracle and OpenAI, 23 Sep 2025
Campus power1.2 GW across eight buildings by end-2026Crusoe, 27 Mar 2026
Per building100 MW of IT load, four halls of 25 MWDPR, undated project page
Estimated operating0.3 GW, four of eight buildingsEpoch AI, 23 Apr 2026
A different count10 data centers being builtLarry Ellison, as Wikipedia reports

The one-building and two-building statements were made a week apart in September 2025 and do not match. Both are claims, and neither can be checked from orbit, because a building is roofed long before it is switched on. Sources: Crusoe, 30 September 2025, DPR, Epoch AI and Wikipedia.

The Abilene build, pass by pass

Company statements and our own readings of the pictures, in date order. Use the filters to see one or the other.

  1. 26 Jul 2022

    Scrub pasture

    A USDA aerial photograph shows the site before construction: pasture and ranch roads.

    Pictures
  2. 21 Feb 2024

    No construction

    The Sentinel-2 pass shows untouched scrub across the frame.

    Pictures
  3. 5 Jun 2024

    First cleared ground

    A small cleared patch appears where the first buildings will stand. Crusoe later said construction began in June 2024.

    Pictures
  4. 18 Jul 2024

    200 MW, expanding to 1.2 GW

    Crusoe and Lancium announce the first phase on the Lancium Clean Campus, to be energised in 2025.

    Statements
  5. 10 Sep 2024

    A pad and two footprints

    A graded pad with the outlines of two buildings.

    Pictures
  6. 15 Oct 2024

    $3.4 billion for the first two buildings

    Crusoe, Blue Owl and Primary Digital Infrastructure fund a 206 MW, two-building project, leased to an unnamed Fortune 100 hyperscale tenant.

    Statements
  7. 29 Dec 2024

    Two buildings roofed

    Both buildings of the first phase are under roofs.

    Pictures
  8. 27 Mar 2025

    A second pad

    A large area south of the first buildings is graded, with building pads on it by late April.

    Pictures
  9. Jun 2025

    First chips

    Oracle begins delivering NVIDIA GB200 racks, according to Crusoe and OpenAI.

    Statements
  10. 9 Aug 2025

    Six more buildings framed

    Four buildings in a row and two to the west, with walls up and roofs in progress.

    Pictures
  11. 23 Sep 2025

    Eight buildings, one running

    Oracle and OpenAI say one building is up and running, seven more are due by mid-2026, and a further 600 MW may follow nearby.

    Statements
  12. 30 Sep 2025

    Two buildings energised

    Crusoe says the first two buildings are energised and the campus is running early training and inference workloads.

    Statements
  13. 27 Dec 2025

    Six more roofed

    The row of four and the western pair are roofed, with equipment rows along them.

    Pictures
  14. 26 Mar 2026

    All eight halls roofed

    Eight roofed halls stand in three groups, and new ground has been cleared to the south.

    Pictures
  15. 27 Mar 2026

    1.2 GW, and a campus for Microsoft

    Crusoe says the eight-building campus will reach 1.2 GW by the end of 2026, and announces a separate 900 MW, two-building campus for Microsoft, with land clearing under way.

    Statements
  16. 23 Apr 2026

    Four of eight operational, estimated

    Epoch AI estimates about 0.3 GW in operation, rising to 1.2 GW by the fourth quarter of 2026.

    Estimates
  17. 4 Nov 2026

    Yards fitted out, new buildings to the south

    Equipment rows line the eight halls, and large buildings are rising on the ground cleared south of them since spring.

    Pictures

Then and now: the Abilene site from orbit

Before and after: scrub pasture outside Abilene in June 2023, and the Stargate data center campus with eight roofed halls in November 2026.
The same frame, 40 months apart. Drag the handle to compare. Contains modified Copernicus Sentinel data 2023 and 2026.

In the November 2026 pass the eight halls stand in three groups: two to the north, four in a row through the middle and two to the west, each with the repeating rooftop pattern of a data hall and rows of equipment beside it. South of them, buildings are rising on ground first cleared in March 2026.

  • What the picture shows: ground, walls, roofs, yards, roads and car parks, at 10 metres per pixel.
  • What it cannot show: whether a hall is switched on, how many chips are inside, or how much of the 1.2 GW has been delivered.
  • How often: a clear pass most weeks in West Texas; this guide uses the clearest one in each quarter.

Power, water and jobs, as stated

Every figure below is a claim, with whose it is and when it was made. Where two sources disagree, both are shown.

ClaimWho, when
GridConnects directly to the ERCOT gridOracle and OpenAI, Sep 2025
On-site powerGE Vernova gas turbines, for backupOracle and OpenAI, Sep 2025
RenewablesNearby wind; possible on-site solarFinancing release, Oct 2024
CoolingClosed-loop, non-evaporative liquid coolingOracle and OpenAI, Sep 2025
Water, fact sheetAbout 12,625 gallons per building a yearOracle and OpenAI, Sep 2025
Water, Oracle's pageRoughly 50,000 gallons per building a yearOracle, as of Jan 2026
Construction workersMore than 6,400 on site every dayOracle and OpenAI, Sep 2025
Permanent jobs, earlyAlmost 100 local jobsFinancing release, Oct 2024
Permanent jobs, laterNearly 1,700, campus and expansionOracle and OpenAI, Sep 2025
Local economyNearly $1 billion over 20 yearsDevelopment Corporation of Abilene, as cited Oct 2024
Property taxUp to 32% of the city's budgeted levyCrusoe, Mar 2026, for the first eight buildings
GPUs per buildingUp to 100,000Crusoe, Jul 2024
GPUs, whole campusHundreds of thousandsCrusoe, Sep 2025

Crusoe's property-tax line refers to the city of Abilene's 2025 budgeted property-tax revenue, and up to 25% of Taylor County's (Crusoe, 27 March 2026). Texas Standard quoted a local official on an 85% property tax break over 10 years (Texas Standard). Oracle's page says it is current as of January 2026 and will not be updated (Oracle).

Who owns and runs the Abilene data center?

  • Crusoe builds, owns and operates the data center (Lancium, July 2024).
  • Lancium assembled the land and the power connection for the Lancium Clean Campus.
  • Blue Owl and Primary Digital Infrastructure funded the first two buildings through a $3.4 billion joint venture (Crusoe, October 2024).
  • Oracle runs Oracle Cloud Infrastructure in the buildings, and OpenAI calls the campus the flagship of Stargate (OpenAI).
  • Microsoft is the customer for the separate 900 MW campus Crusoe announced next door in March 2026.

Stargate itself, the venture of OpenAI, Oracle and SoftBank, and its other sites are covered in the AI data center guide.

Abilene data center: questions and answers

Follow Stargate Abilene on Track

A hand-built board on the biggest AI campuses, with a satellite-backed reading after each clear pass and the history in one place. Free while Aureum is in beta.