xAI Colossus

Colossus data center: Memphis, Southaven, and the counts that do not match

Two sites and a power plant across a state line, seen from orbit.

xAI's Colossus began in a former factory in South Memphis in 2024. A second site in Whitehaven followed, with buildings and turbines across the state line in Southaven, Mississippi. This guide sets satellite pictures of both sites beside the GPU, turbine and power figures each source states, with a date on every one.

Aureum reference guide · Latest passes 16 Sep and 6 Oct 2026

Watch Colossus 2 go up

Nine clear Sentinel-2 passes over the same 3.3 by 3.5 km frame, from December 2024 to October 2026. The frame straddles the Tennessee and Mississippi state line, which runs just north of Stateline Road here: the warehouse near the top is in Whitehaven, Memphis, and the newer buildings to the south are in Southaven.

Sentinel-2 picture of xAI's Colossus 2 site in Whitehaven, Memphis, and Southaven, Mississippi, 6 OCT 20266 OCT 2026
Sentinel-2 true colour, the clearest pass in each quarter, all cropped to the same frame. Contains modified Copernicus Sentinel data 2024 to 2026.

What the passes show: the large warehouse near the top of the frame was already standing. By May 2025 a big pad beside it is graded; by the end of 2025 buildings and equipment stand on it; and by October 2026 long roofed buildings fill it, with more ground cleared to the west. About 2 km to the south, across the state line in Southaven, new ground is graded around an existing industrial site from May 2025, and by October 2026 it has grown into a large complex of structures. No source we have read says which of the Southaven sites that complex is.

Status checkChecked

How big is Colossus?

There is no agreed figure. xAI's own Colossus page still describes the first machine; the trackers measure different kinds of power; and the turbine counts describe different yards on different days. These are the latest figures, each with what it measures.

xAI's Colossus page
200,000 GPUs: built in 122 days, then doubled in 92The page still describes the first machine and carries a February 2025 date.x.ai/colossus
Wikipedia
440,000 GB300s in use at Colossus 2 by late September 2026With 660,000 more expected by the end of 2026. Article edited 31 Oct 2026.Wikipedia
Cleanview
Colossus 2: 1,836 MW operating, 2,844 MW at full build-outFacility power, first on its US operating list. Read 6 Nov 2026.Cleanview
Epoch AI
Colossus 2: 946 MW of IT powerIT power only, which Epoch puts 20% to 50% below facility power. Read 6 Nov 2026.Epoch AI
NAACP, SELC and Earthjustice
27 gas turbines in Southaven, up to 495 MW, without permitsTheir allegation, in a notice of intent to sue of 13 Feb 2026.NAACP, 13 Feb 2026
Aureum satellite passes
Dark arrays at Colossus 1 (16 Sep); a growing Southaven complex (6 Oct)Sentinel-2B passes. Long roofed buildings now fill the pad beside the Colossus 2 warehouse. See Colossus 1 and the Colossus 2 sequence.

This panel is the only part of the page tied to a date. Everything below it is background, with the period stated on every figure.

Fact file

Colossus at a glance

The background figures, each with who stated it and when.

Colossus 1
3231 Paul R. Lowry Road
South Memphis, the address in the June 2025 notice of intent (SELC for the NAACP).
The building
A former Electrolux factory
As Wikipedia describes it; the 2023 aerial photographs show the plant before xAI.
Running since
June 2024
When xAI began operations in South Memphis, according to the NAACP.
First machine
100,000 GPUs
NVIDIA Hoppers, built with NVIDIA in 122 days (NVIDIA, October 2024).
Doubled to
200,000 GPUs
In 92 days, according to xAI's Colossus page.
Turbines, Colossus 1
15 permitted, 12 sought
Permits for 15 (NAACP, February 2026); a request to cut that to 12 (public notice, April 2026).
Colossus 2
Whitehaven, Memphis
A warehouse site in south Memphis, with newer buildings across the state line in Southaven.
Colossus 2 running since
Late 2025
According to the NAACP, February 2026.
Southaven turbines
27, up to 495 MW
The groups' allegation, February 2026.
Permanent power plant
About 1.2 GW, 41 turbines
Permitted in March 2026, as Wikipedia reports.
Company
xAI, now part of SpaceX
Scientific American reports the acquisition; xAI's Memphis page uses the name SpaceXSI.
Renter
Anthropic, at Colossus 1
Agreed in May 2026 to rent essentially all of Colossus 1, as Wikipedia reports.

Sources: SELC notice of intent (17 June 2025), NAACP (17 June 2025 and 13 February 2026), NVIDIA (28 October 2024), xAI, Wikipedia (edited 31 October 2026) and Scientific American.

Where is the Colossus data center?

Colossus is not one building. Colossus 1 is in South Memphis, at 3231 Paul R. Lowry Road (SELC notice, June 2025), in what Wikipedia describes as a former Electrolux appliance factory (Wikipedia). Colossus 2 began at a warehouse site in Whitehaven, about 13 km to the south-east, and has spread across the state line into Southaven, Mississippi, where the groups suing xAI say its turbines stand.

  • Colossus 1, South Memphis: the first site, running since June 2024, by the NAACP's account.
  • Colossus 2, Whitehaven: a warehouse and parcels bought in early 2025, with its roof branded Macrohard, as Wikipedia describes them.
  • Southaven, Mississippi: a turbine plant on the former Duke Energy site on Stanton Road (Wikipedia), and two further data center sites that xAI calls Gun Range and Spam: two single-storey buildings on 55.9 acres and a single-storey warehouse on 53 acres (Data Center Dynamics).

Colossus 1: the first site

xAI began operating in South Memphis in June 2024, according to the NAACP (NAACP, June 2025). In October 2024 NVIDIA said the facility and supercomputer, 100,000 Hopper GPUs, had been built in 122 days, with 19 days from the first rack to training, and that xAI was doubling it to 200,000 (NVIDIA). xAI's own Colossus page still tells that story: 122 days to build, 92 to double (xAI).

Sentinel-2 picture of xAI's Colossus 1 site in South Memphis, 16 SEP 202616 SEP 2026
Colossus 1, ten clear Sentinel-2 passes over the same 2.6 by 2.1 km frame, February 2024 to September 2026. Contains modified Copernicus Sentinel data 2024 to 2026.

From orbit, the change at Colossus 1 is in the yards rather than the building, which was already standing. The ground west and south of it, bare in the 2023 aerial photograph and grassed over by June 2024, is bare again from the 26 September 2024 pass; small structures and equipment appear along the building's north and east sides in 2025; and between 28 February and 16 September 2026, rows of large dark arrays cover the ground west of the building. The pictures do not say what they are.

USDA aerial photograph of the South Memphis factory that became Colossus 1, with its car parks and bare ground to the west and south, May 2023.
The Colossus 1 site on 3 May 2023, before xAI: the factory, its car parks and bare ground to the west and south, in the same frame as the sequence. USDA National Agriculture Imagery Program, 60 cm, public domain.

The site's turbines are the most disputed thing about it. The NAACP said in June 2025 that aerial images showed 35 turbines there in March of that year; in February 2026 it said xAI had removed its unpermitted turbines and obtained permits for the remaining 15 (NAACP, February 2026). A Shelby County Health Department notice of 7 April 2026, as reproduced online, records a request to cut the permitted turbines from 15 to 12. Wikipedia reports that Anthropic agreed in May 2026 to rent essentially all of Colossus 1.

Colossus 2 and the Southaven sites

The NAACP placed xAI's second South Memphis data center in Whitehaven in June 2025, and said in February 2026 that it had begun operating in late 2025. Wikipedia describes a warehouse and parcels bought in early 2025 and a first cluster of about 110,000 GB200-class chips, roughly 210 MW, online around January 2026.

USDA aerial photograph of Whitehaven and northern Southaven in May 2023, with the large warehouse that became Colossus 2 near the top.
The Colossus 2 frame on 3 May 2023: the warehouse near the top was already built, and the ground to the south was largely woodland and open land around an existing industrial site. USDA National Agriculture Imagery Program, 60 cm, public domain.

Musk has said the two newer Southaven sites, Gun Range and Spam, would be operating by the end of 2026, with about 420,000 GB300 chips between them, as Data Center Dynamics reports. On 30 July 2026 xAI's Memphis page noted an agreed order with Mississippi's environmental regulator on a fixed timeline to remove the temporary turbines in Southaven (xAI).

Before and after: the Whitehaven warehouse and woodland to the south in December 2024, and the Colossus 2 buildings and the Southaven complex in October 2026.
Colossus 2, 21 months apart. Drag the handle to compare. Contains modified Copernicus Sentinel data 2024 and 2026.

The Colossus build, step by step

Company, campaign and regulator statements, and our own readings of the pictures of both sites, in date order. Use the filters to see one or the other.

  1. Jun 2024

    Colossus 1 running

    xAI begins operating in South Memphis, according to the NAACP.

    Statements
  2. 13 Jun 2024

    A factory in a field

    Colossus 1: the former factory stands among grass and woodland; the ground west of it, bare in 2023, has grassed over.

    Pictures
  3. 26 Sep 2024

    Bare ground again

    Colossus 1: the ground west and south of the building is bare again.

    Pictures
  4. 28 Oct 2024

    100,000 GPUs in 122 days

    NVIDIA says the facility and supercomputer were built in 122 days, and that xAI is doubling it to 200,000 GPUs.

    Statements
  5. 30 Dec 2024

    A warehouse in Whitehaven

    Colossus 2: the large warehouse stands beside partly cleared ground; woodland covers most of the land to the south.

    Pictures
  6. Feb 2025

    Whitehaven bought

    xAI buys the warehouse and parcels for roughly $80 million, as Wikipedia reports. Data Center Dynamics dates the purchase to March.

    Statements
  7. Mar 2025

    35 turbines at Colossus 1

    Aerial images obtained by SELC show 35 turbines at the site, the NAACP says.

    Statements
  8. 21 May 2025

    Two sites graded

    Colossus 2: a large pad beside the warehouse is graded, and new ground is cleared around an existing industrial site about 2 km south, in Southaven.

    Pictures
  9. 17 Jun 2025

    Notice of intent to sue

    SELC, for the NAACP, alleges xAI has run at least 35 combustion turbines at Colossus 1 without air permits.

    Statements
  10. 2 Jul 2025

    15 turbines permitted

    The Shelby County Health Department permits 15 turbines at Colossus 1, as Wikipedia reports.

    Statements
  11. Late 2025

    Colossus 2 running

    The NAACP says Colossus 2 began operating in late 2025. Wikipedia dates a first cluster of about 110,000 GB200-class chips, about 210 MW, to around January 2026.

    Statements
  12. 30 Dec 2025

    Buildings on the pad

    Colossus 2: buildings and equipment stand on the pad beside the warehouse, and the Southaven site has spread over a larger graded area.

    Pictures
  13. 13 Feb 2026

    27 turbines in Southaven

    The NAACP, SELC and Earthjustice give notice over 27 gas turbines in Southaven, up to 495 MW, which they say run without permits.

    Statements
  14. Mar 2026

    A permanent plant permitted

    A permanent plant of about 1.2 GW and 41 turbines receives its air permit, as Wikipedia reports.

    Statements
  15. 7 Apr 2026

    From 15 turbines to 12

    A Shelby County Health Department notice records a request to cut Colossus 1's permitted turbines from 15 to 12.

    Statements
  16. May 2026

    Anthropic rents Colossus 1

    Anthropic agrees to rent essentially all of Colossus 1, as Wikipedia reports.

    Statements
  17. 30 Jul 2026

    A removal order in Mississippi

    xAI's Memphis page notes an agreed order with Mississippi's environmental regulator on a timeline to remove the temporary Southaven turbines.

    Statements
  18. 16 Sep 2026

    Dark arrays at Colossus 1

    Rows of large dark arrays cover the ground west of the building. The pictures do not say what they are.

    Pictures
  19. Late Sep 2026

    440,000 GB300s

    Wikipedia reports 440,000 GB300 chips in use at Colossus 2, with 660,000 more expected by the end of 2026.

    Statements
  20. 6 Oct 2026

    Roofed buildings, a growing complex

    Colossus 2: long roofed buildings fill the pad beside the warehouse, more ground is cleared to the west, and the Southaven complex has spread west.

    Pictures

How many turbines does Colossus have?

The pages count different things: turbines installed, permitted, temporary or permanent, or the megawatts they could produce. These are the counts, each with what it describes.

CountWhat it describesWho, when
Colossus 1, 2025At least 35Turbines run without permits, allegedSELC notice, 17 Jun 2025
Colossus 1, permitted15Turbines with permits in Shelby CountyNAACP, Feb 2026
Colossus 1, sought12A requested cut from 15 to 12Public notice, 7 Apr 2026
Southaven, early 202627, up to 495 MWTurbines installed without permits, allegedNAACP, SELC and Earthjustice, 13 Feb 2026
Southaven, by July69Temporary turbines counted by Mississippi regulatorsScientific American, year not stated
Southaven, range50 to 70Temporary turbines, as reportedWikipedia, 31 Oct 2026
Permanent plant41, about 1.2 GWPermitted in March 2026Wikipedia, 31 Oct 2026

These can all be true at once, of different yards on different days; written as one number, they contradict each other. Wikipedia reports that the temporary units are due to be removed by mid-2027 (SELC; Scientific American; Wikipedia).

The power figures, named

FigureWhat it measuresWho, when
Cleanview, operating1,836 MWFacility power of Colossus 2 buildings running todayRead 6 Nov 2026
Cleanview, full build-out2,844 MWEverything planned at Colossus 2Read 6 Nov 2026
Epoch AI946 MWIT power at Colossus 2Read 6 Nov 2026
Wikipedia, first clusterAbout 210 MWColossus 2's first cluster, around January 2026Edited 31 Oct 2026
Wikipedia, combinedOn the order of 1 GWAll sites, as of mid-2026Edited 31 Oct 2026
Data Center Dynamics350 MWCooling seen in January satellite imagery, as reportedArticle date not stated
SELC495 MWPotential output of 27 Southaven turbines14 Apr 2026

No average of these means anything: facility power, IT power, cooling capacity and turbine output are different quantities. A 10-metre picture cannot measure any of them. It can show where buildings, pads and equipment yards are, and when they appeared.

Colossus data center: questions and answers